News:

FORUM HAS BEEN UPGRADED  - if you have trouble logging in, please tap/click "home"  and try again. Hopefully this upgrade addresses recent server issues.  Thank you for your patience. Forum Manager

MESSAGE ABOUT WEBSITE REGISTRATIONS
http://mahoningvalley.info/forum/index.php?topic=8677

Main Menu

West Side Library Progress Report

Started by jay, June 28, 2017, 10:16:34 AM

Previous topic - Next topic

0 Members and 1 Guest are viewing this topic.

cc4

The maker space seems to be wildly popular.  There are many more reasons to


stop in and look around if you haven't already done so.

iwasthere


jay

A bike rack has been installed near the entrance to the library.

jay

The railings are being installed on the front steps today.

jay

The words Michael Kusalaba Library have been attached to the front and east outside walls of the library.

iwasthere

Finally the indoor plygrd equipment will be installed. I can hardly wait to hear screaming joyous little voices inside a once quite library setting.

jay

Straw has been applied to the seeded area in front and on the side of the new library.

From now on, most of the future work will take place inside the building.

jay

Topsoil has now been placed on the ground in front of the building.  I suspect that sod will be installed next.

iwasthere

has the indoor playgrd been installed?

jay

A grove of sugar maple trees has now been planted around the parking lot.

jay

New sidewalks were installed along S. Schenley and Mahoning Avenue this week.

jay

Shrubs were planted along the east and north sides of the new building.

iwasthere

Is the indoor playgrd equipment on order?

jay

Construction work should be finished by late December.   The library system will move in books and furniture in early January.  Our new library should open by the end of January.

jay

Wood-like panels are now being installed on the front of the building.