New sidewalks were installed along S. Schenley and Mahoning Avenue this week.

jay:
Shrubs were planted along the east and north sides of the new building.

iwasthere:
Is the indoor playgrd equipment on order?

jay:
Construction work should be finished by late December.   The library system will move in books and furniture in early January.  Our new library should open by the end of January.

jay:
Wood-like panels are now being installed on the front of the building.