The parking lot and driveway at the Mill Creek Plaza are being resurfaced.  Phase one was done today.   That's the area in front of the three stores facing S. Schenley.
Title: Re: Mill Creek Plaza Resurfacing
Post by: jay on August 02, 2016, 10:56:14 AM
The paving company is working on phase two today.  It's the area northeast of the plaza.
Title: Re: Mill Creek Plaza Resurfacing
Post by: jay on August 05, 2016, 05:27:06 AM
The yellow parking space lines have been painted.

The project is finished.