Author Topic: West Side Library Progress Report  (Read 124 times)

0 Members and 1 Guest are viewing this topic.

Offline iwasthere

  • Platinum Member
  • *****
  • Posts: 4338
Re: West Side Library Progress Report
« Reply #5 on: September 14, 2017, 09:51:44 PM »
Is the indoor playgrd equipment on order?

Offline jay

  • Global Moderator
  • Platinum Member
  • *****
  • Posts: 17471
  • Support Youngstown Businesses
Re: West Side Library Progress Report
« Reply #4 on: September 14, 2017, 07:28:17 PM »
Construction work should be finished by late December.   The library system will move in books and furniture in early January.  Our new library should open by the end of January.

Offline jay

  • Global Moderator
  • Platinum Member
  • *****
  • Posts: 17471
  • Support Youngstown Businesses
Re: West Side Library Progress Report
« Reply #3 on: August 09, 2017, 03:30:10 PM »
Wood-like panels are now being installed on the front of the building.

Offline iwasthere

  • Platinum Member
  • *****
  • Posts: 4338
Re: West Side Library Progress Report
« Reply #2 on: June 28, 2017, 01:30:23 PM »
When are they going to install the inside playground equipment?

Offline jay

  • Global Moderator
  • Platinum Member
  • *****
  • Posts: 17471
  • Support Youngstown Businesses
West Side Library Progress Report
« Reply #1 on: June 28, 2017, 10:16:34 AM »
They are installing the front windows today.